Master Bathroom Remodel on Richmond Ave, Richmond
A master bathroom remodel with a new tiled shower, new bathtub and toilet, new vanity with a stone top, and new lighting and electrical. Completed in February 2025 for $24,000-$29,000.
Client
Nicholas B.
Richmond Ave, Richmond
Investment
$24,000-$29,000
Project range
Completed
February 2025
Master bathroom remodel
Project
Master Bathroom Remodel
Richmond Ave, Richmond

The finished bathroom on Richmond Ave in Richmond.
4.6
Google rating
53
Google reviews
18+
Years in business
700+
Projects completed
The Brief
Nicholas B. asked Heroes Services to remodel the master bathroom in his home on Richmond Ave in Richmond. The plan was to remove the old shower, bathtub, vanity, fixtures, tile and flooring, and build a new bathroom with a tiled shower, new bathtub and toilet, new vanity with a stone top, and new lighting and electrical.
The work was completed in February 2025 for $24,000-$29,000. The homeowner supplied the tile, vanity, fixtures, mirror and shower glass, and Remodeling Heroes provided the labor.
What We Did
- Removed the old shower, bathtub, vanity, fixtures, tile and flooring.
- Installed new 12x24 porcelain floor tile over cement board with Schluter waterproofing.
- Tiled the shower to the ceiling with a built-in niche and Schluter metal trim.
- Relocated the plumbing and installed a new shower valve and two shower heads.
- Installed a new bathtub and toilet.
- Added recessed lights and a sconce, and installed GFCI outlets and an exhaust fan.
- Installed the vanity with a stone top.
- Primed and painted the walls and ceiling.
- The homeowner supplied the tile, vanity, fixtures, mirror and shower glass, and Remodeling Heroes provided the labor.
Project at a Glance
- Location
- Richmond Ave, Richmond
- Project
- Master Bathroom Remodel
- Completed
- February 2025
- Investment
- $24,000-$29,000
How It Came Together
Step 1
Remove the Old Bathroom
We removed the old shower, bathtub, vanity, fixtures, tile and flooring, and prepared the room for the new bathroom.
Step 2
Tile and Waterproofing
We installed new 12x24 porcelain floor tile over cement board with Schluter waterproofing, and tiled the shower to the ceiling with a built-in niche and Schluter metal trim.
Step 3
Plumbing and Fixtures
We relocated the plumbing, installed a new shower valve and two shower heads, and installed a new bathtub and toilet.
Step 4
Vanity, Lighting and Paint
We installed the vanity with a stone top, added recessed lights and a sconce, installed GFCI outlets and an exhaust fan, then primed and painted the walls and ceiling.
The finished bathroom
Photos from the finished bathroom on Richmond Ave in Richmond.









Frequently Asked Questions
What did this master bathroom remodel include?
We removed the old shower, bathtub, vanity, fixtures, tile and flooring. We installed new 12x24 porcelain floor tile over cement board with Schluter waterproofing, tiled the shower to the ceiling with a built-in niche and Schluter metal trim, relocated the plumbing, and installed a new shower valve and two shower heads. We also installed a new bathtub and toilet, a vanity with a stone top, recessed lights and a sconce, GFCI outlets and an exhaust fan, and primed and painted the walls and ceiling.
What was the investment?
The project investment was $24,000-$29,000.
When was it completed?
This master bathroom remodel was completed in February 2025.
Who supplied the materials?
The homeowner supplied the tile, vanity, fixtures, mirror and shower glass, and Remodeling Heroes provided the labor.